Request Summary
Change to the current SWEDE Transmission Requirement in Tariff Section 19.4
Co-sponsors
Description Of Issue
The current transmission requirement in the tariff for the SWEDE region requires transmission to be demonstrated no less than the surplus or deficit calculation MW quantity. This requirement may harm Southwest participants and should not be necessary in order for WRAP to succeed.
Proposed Solution
Remove existing tariff language and add in additional language to be consistent with the current understanding of the transmission requirement for clarity.
Specific Document And Language
Current Tariff Language: 19.4 Each Participant in any Subregion identified in the Business Practice Manuals as not containing a central transmission hub permitting energy deliveries to that hub from any point within such Subregion, shall, in addition to providing the information required by Section 19.3, identify, on or before the deadline during the Preschedule Day specified in the Business Practice Manuals, for each Hour of the Operating Day each point to which it can deliver energy, each point at which it can take receipt of energy, the quantity it can deliver or receive at each such point, and a numeric factor intended to prioritize use of transmission made available by Participants with positive Sharing Calculations and needed by Participants with negative Sharing Calculations for each such hour. A Participant with a positive Sharing Calculation for an hour must provide a total quantity for all identified points at which it can deliver that is no less than the amount of its positive Sharing Calculation for such hour (adjusted as necessary for any RA Transfer in accordance with Section 20.1.2). A Participant with a negative Sharing Calculation for an hour must provide a total quantity for all identified points at which it can take receipt that is no less than the amount of its negative Sharing Calculation for such hour (adjusted as necessary for any RA Transfer in accordance with Section 20.1.2). Participants shall provide this same information for each Operating Day on an expected or preliminary basis on each day of the Multi-Day-Ahead Assessment following, and based on, the expected Holdback Requirement estimates provided on each such day for the Operating Day.
Suggested Language Update
Proposed Change: 19.4 Each Participant in any Subregion identified in the Business Practice Manuals as not containing a central transmission hub permitting energy deliveries to that hub from any point within such Subregion, shall, in addition to providing the information required by Section 19.3, identify, on or before the deadline during the Preschedule Day specified in the Business Practice Manuals, for each Hour of the Operating Day each point to which it can deliver energy, each point at which it can take receipt of energy, the quantity it can deliver or receive at each such point, and a numeric factor intended to prioritize use of transmission made available by Participants with positive Sharing Calculations and needed by Participants with negative Sharing Calculations for each such hour. A Participant with a positive Sharing Calculation or a negative Sharing Calculation for an hour must provide a total quantity for all identified points that is either available per OASIS or reserved by the participant. at which it can deliver that is no less than the amount of its positive Sharing Calculation for such hour (adjusted as necessary for any RA Transfer in accordance with Section 20.1.2). A Participant with a negative Sharing Calculation for an hour must provide a total quantity for all identified points. at which it can take receipt that is no less than the amount of its negative Sharing Calculation for such hour (adjusted as necessary for any RA Transfer in accordance with Section 20.1.2). Participants shall provide this same information for each Operating Day on an expected or preliminary basis on each day of the Multi-Day-Ahead Assessment following, and based on, the expected Holdback Requirement estimates provided on each such day for the Operating Day.
Benefits
The current tariff requirement did not contemplate the potentially large sharing calculation results that could occur. This requirement could result in harm to a participant that is not necessary for a successful program.
Data Or Information