COMMENT FOR BPM 108 - Forward Showing Submittal Process

Submitted Jan. 5, 2024, 2:36 p.m.



01: Please supply any comments related to the Introduction, Definitions, or Background sections.

No response submitted.

02: Please supply any comments related to the Forward Showing Submittal and Cure Period section (2).

FS Cure deadlines are set dates in this BPM. The Tariff language in 13.2.(iii) states that the "Participant shall have an opportunity to cure such deficiencies, within sixty days of notification of deficiency" Is this document clarifying that the PO deficiency notices will never be sent before the dates specified? It would help to clarify the gap between Tariff language and the BPM.

03: Please supply any comments related to the Forward Showing Submittal Materials section (3).

No response submitted.

04: Please supply any comments related to the Forward Showing Submittal Materials - FS Demonstration section (3.1).

No response submitted.

05: Please supply any comments related to the Forward Showing Submittal Materials - Loads section (3.1.1).

No response submitted.

06: Please supply any comments related to the Forward Showing Submittal Materials section - Qualifying Resources section (3.1.2).

No response submitted.

07: Please supply any comments related to the Forward Showing Submittal Materials - Contracts section (3.1.3).

No response submitted.

08: Please supply any comments related to the Forward Showing Submittal Materials - Transmission section (3.1.4).

It might be helpful to clarify that conditional firm transmission is acceptable in addition to listing the NERC priority codes.

3.1.4.1.2: Should be listed as "NERC Priority 6 or NERC Priority 7 firm point-to-point transmission service or network integration transmission service (NITS)" for clarity

For Bullet #3 in this section, is NITS an option for this criteria?

09: Please supply any comments related to the Forward Showing Submittal Materials - Planned Outages section (3.1.5).

What is the QCC for resources that are out 1 to 4 days of a month? Does this have to be the first four days of the month?

Any guidance on how to handle outages that are only a few days of a month or a part of the month will be helpful.

There is language for outages at the time of FS filing, and for outages after FS filing. There is language for the number of days out in the first five days part of the FS season. There is attestation possibilities under two different scenarios. Could you please provide a Table to help clarify what the requirements are? It is difficult to decipher the requirements from the language in this section.

This section could also clarify which of the two different classes of outages specified are to be in included in the FS workbook.

10: Please supply any comments related to the Forward Showing Supporting Materials section (3.2).

No response submitted.

11: Please supply any comments related to the Forward Showing Supporting Materials - Testing section (3.2.1).

Please provide details on the nature and format of how these test results are to be submitted. If this is described in another BPM, please name the BPM here and/or provide a link on the WPP website.

12: Please supply any comments related to the Forward Showing Supporting Materials - Thermal Resources that are not Required to Report GADS Data section (3.2.2).

No response submitted.

13: Please supply any comments related to the Forward Showing Supporting Materials - Hydro Resources section (3.2.3).

No response submitted.

14: Please supply any comments related to the Forward Showing Supporting Materials - Late Registered Resources section (3.2.4).

No response submitted.

15: Please supply any comments related to the Forward Showing Supporting Materials - Transition Exceptions section (3.2.5).

No response submitted.

16: Please supply any comments related to the Cure Period section (4).

No response submitted.

17: Please supply any comments related to Appendix A.

No response submitted.

18: Please supply any comments related to Appendix B.

No response submitted.

19: Please supply any comments related to Appendix C and D.

No response submitted.

20: Please supply any comments related to Appendix E.

No response submitted.

21: Please supply any comments related to Appendix F.

No response submitted.

22: Please supply any comments related to Appendix G.

No response submitted.

General Comment