COMMENT FOR BPM 101 - Advance Assessment

Submitted Oct. 6, 2023, 9:21 p.m.



01: Please supply any comments related to the Introduction, Definitions, or Background sections.

No response submitted.

02: Please supply any comments related to the Advance Assessment Timeline section.

PAC believes participants would benefit from a centralized, live, rolling calendar of these activities and milestones (like today's BPM tracker) to help ensure participants are informed and prepared for various upcoming data submittals and reviews. 

03: Please supply any comments related to the Data Submittal section.

No response submitted.

04: Please supply any comments related to the Data Submittal - Advance Assessment Submittal Process section (3.1).

No response submitted.

05: Please supply any comments related to the Data Submittal - Resource Registration Implication section (3.2).

PAC would appreciate elaboration on the topic of resources with planned reitirement dates within the study period. This section states participants have the option to submit such resources into the LOLE/FSPRM assessment, or not. PAC would appreciate this BPM include the effects and any potential risks associated with choosing one option versus the other.

06: Please supply any comments related to the Data Submittal - Modeling Data from Forward Showing Submittal section (3.3).

No response submitted.

07: Please supply any comments related to the Data Submittal - Participant Review and Verification Process of Input Data section (3.4).

-If during this data review a participant discovers a discrepancy, can it be corrected without penalty? 

-What kind of confirmation will the Program Operator be seeking from participants once the input data has been reviewed? RAPC attestation? Simple email? Something else?

08: Please supply any comments related to the Draft Modeling Output Results Review section (3.5).

No response submitted.

09: Please supply any comments related to the Data Submittal - Advance Assessment Result Distribution section (3.6).

No response submitted.

General Comment

Pacificorp appreciates the ongoing work of WPP and the opportunity to comment on BPM 101.