COMMENT FOR BPM 108 - Forward Showing Submittal Process

Submitted Jan. 4, 2024, 4:16 p.m.



01: Please supply any comments related to the Introduction, Definitions, or Background sections.

None

02: Please supply any comments related to the Forward Showing Submittal and Cure Period section (2).

A "PM" was likely omitted from the section. A deadline of 05:00 for the Forward Showing Submittal seems out of place. 17:00 or some other time during normal business hours seems more appropriate.

03: Please supply any comments related to the Forward Showing Submittal Materials section (3).

None

04: Please supply any comments related to the Forward Showing Submittal Materials - FS Demonstration section (3.1).

None

05: Please supply any comments related to the Forward Showing Submittal Materials - Loads section (3.1.1).

None

06: Please supply any comments related to the Forward Showing Submittal Materials section - Qualifying Resources section (3.1.2).

None

07: Please supply any comments related to the Forward Showing Submittal Materials - Contracts section (3.1.3).

PAC will look forward to the opportunity to review and comment upon BPM 106, once published. PAC anticipates WPP will address the JCAF requirement within BPM 106.

08: Please supply any comments related to the Forward Showing Submittal Materials - Transmission section (3.1.4).

None

09: Please supply any comments related to the Forward Showing Submittal Materials - Planned Outages section (3.1.5).

PAC would appreciate additional clarity in this section in regard to how planned outages affect resource QCCs in the Forward Showing.

PAC is lead to understand by the language of this section any planned outage for a resource lasting five or more days reduces the resource's QCC to zero for the given month in the Forward Showing. 

The following passage implies potential different treatment for resources offline at the time of Forward Showing submittal whose outages will extend into the binding season, versus resources available at the time of FS submittal but with planned outages overlapping with the binding season. The passage does not clearly address the latter these implied categories, into which most planned outages would likely to fall:

"Any Qualifying Resource that is out of service at the time of the FS Deadline and is planned to remain out of service for five or more days of a month in the Binding Season cannot have such Qualifying Resource’s QCC counted toward meeting the Participant’s FS Capacity Requirement for that month"

PAC would suggest a resource QCC reduction proportional to expected resource availability during the binding month, instead of the all-or-nothing approach of this BPM. PAC would prefer something like a "planned outage factor" to apply to the monthly QCC. This would be calculated and applied as follows: (# of days resource is available / # of total days in month) * QCC. 

PAC further notes planned outages are often intended to be contained to shoulder months, but personnel, parts or schedule availability may force planned outages to be scheduled into the the early weeks of June or November, when RA risk is generally low. 
 

10: Please supply any comments related to the Forward Showing Supporting Materials section (3.2).

PAC would appreciate any forms required in the Forward Showing to be included as appendices to the BPM. The form itself may impose requirements not mentioned in the parent BPM or WRAP tariff. By leaving the forms out of the BPM, requirements can be imposed, and modifications to the forms can potentially be made outside of a governance or review process.

11: Please supply any comments related to the Forward Showing Supporting Materials - Testing section (3.2.1).

None

12: Please supply any comments related to the Forward Showing Supporting Materials - Thermal Resources that are not Required to Report GADS Data section (3.2.2).

None

13: Please supply any comments related to the Forward Showing Supporting Materials - Hydro Resources section (3.2.3).

None

14: Please supply any comments related to the Forward Showing Supporting Materials - Late Registered Resources section (3.2.4).

None

15: Please supply any comments related to the Forward Showing Supporting Materials - Transition Exceptions section (3.2.5).

None

16: Please supply any comments related to the Cure Period section (4).

None

17: Please supply any comments related to Appendix A.

None

18: Please supply any comments related to Appendix B.

None

19: Please supply any comments related to Appendix C and D.

None

20: Please supply any comments related to Appendix E.

None

21: Please supply any comments related to Appendix F.

None

22: Please supply any comments related to Appendix G.

None

General Comment

PacifiCorp appreciates the work of the WPP on BPM 108, and is grateful for the opportunity to comment.

avatar