Neither Table 1 or Table 2 identify a specific delivery date for 'PO provides Participants with draft outputs' does that mean it is part of the general review (September 15, and February 15)?
Table 1 seems to reference the September 15 and February 15 dates as the actual study and not the Advisory by colling them T-2 and T-1.
We need firm expected dates for Advisory outputs to be shared.
Neither Table 1 or Table 2 identify a specific delivery date for 'PO provides Participants with draft outputs' does that mean it is part of the general review (September 15, and February 15)?
Table 1 seems to reference the September 15 and February 15 dates as the actual study and not the Advisory by colling them T-2 and T-1.
We need firm expected dates for Advisory outputs to be shared.
Is March 1st the correct date for the Participant provides data to Program Operator for Advance Assessment? APS only asks because I think we had a January 31st deadline for this year’s Advance Assessment.
Table 1 is very concise and helpful to understand a lot of deadlines quickly and easily!
PAC believes participants would benefit from a centralized, live, rolling calendar of these activities and milestones (like today's BPM tracker) to help ensure participants are informed and prepared for various upcoming data submittals and reviews.