SACHI BEGUR | Puget Sou…
RAJ HUNDAL | PWX
TYLER MOORE | Arizona P…
What is the practical difference between a sale and a transfer? Why do we need a separate type if they are both for the FS? There is also a disconnect here where the contract is submitted to the PO, but for other types of transactions we want to utilize the JCAF to avoid contract submissions. Why not either not require contract submission, since both Participants are submitting it in their FS, or utilize the JCAF/Attestations here as well?
There is a reference here to a seller using NITS which as explained above in prompt # 6 should be modified.
BENJAMIN FAULKINBERRY | PacifiCor…
LINDSEY SCHLEKEWAY | NVE
MATT HAYES | BPA
MICHAEL WATKINS | Seattle C…
City Light has no further comments regarding this section.
JERRET FISCHER | SRP
SRP recommends the WPP include a necessary detail as it relates to any notification and approval process for RA Transfers to enhance clarity and ensure consistency in the application process for all WRAP participants.