01: Please supply any comments related to corrections in the Definitions Section
APS has some comments surrounding the definition and concept of Demand Response Load Modifier that were submitted on BPM 103 and we look forward to the updated version of that BPM.
02: Please supply any comments on redlines to Tariff section 7 (Credit Requirements and Settlement for Holdback and Delivered Energy)
No comments at this time.
03: Please supply any comments related to redlines to Tariff section 10.2 (Treatment of Confidential or Commercially Sensitive Information)
No comments at this time.
04: Please supply any comments related to redlines to Tariff sections 14.2.1.2, 16.1.5, and 19.2 (relating to Forward Showing Submittal demonstration of inter- subregional transmission in lieu of Capacity)
No comments at this time.
05: Please supply any comments on redlines to Tariff sections 16.1.2.1, 16.1.2.3, and 16.2.5.2.2 (related to corrected "annual LOLE" references to "Seasonal LOLE")
No comments at this time.
06: Please supply any comments on redlines to Tariff sections 16.1.2, 16.2.5.4, 20.1.1 (related to options for DR)
See comments on BPM 103 for thoughts on section 16.1.3 and potential reliability impacts of not adding the FPRM on the load reduction allowed with load modification option.
07: Please supply any comments on redlines to Tariff section 16.2.7 (relating to Total RA Transfer)
No comments at this time.
08: Please supply any comments on redlines to Tariff section 16.2.8 (relating to Planned Outages)
No comments at this time.
09: Please supply any comments on redlines to Tariff section 16.3.2 (relating to Transmission Exceptions)
No comments at this time.
10: Please supply any comments on redlines to Tariff sections 17.2.7 and 17.2.8 (relating to Forward Showing Deficiency Charge)
No comments at this time.
11: Please supply any comments on redlines to Tariff section 19.1 (relating to Operations Program Timeline and Supporting Information
No comments at this time.
12: Please supply any comments on redlines to Tariff section 19.4 (relating to Operations Program Timeline and Participant Tx Inputs)
No comments at this time.
13: Please supply any comments on redlines to Tariff section 19.5 and 20.4.1.2 (relating to reference correction of Subregions not containing a central transmission hub)
In 20.4.1.2 propose to include “…unless mutually agreed to by both deficient and surplus Participants”. This would allow for any arrangement where transmission becomes unavailable to be re-supplied at an alternative location.
14: Please supply any comments on redlines to Tariff section 19.5 (relating to decription of mechanics of Voluntary Holdback)
No comments at this time.
15: Please supply any comments on redlines to Tariff section 20.1.1 (relating to update to description of Sharing Calculation)
No comments at this time.
16: Please supply any comments on redlines to Tariff section 20.1.3 (relating to removal of references to lesser priorities of Energy Deployment)
No comments at this time.
17: Please supply any comments on redlines to Tariff section 20.2 (relating to description of mechanics of Holdback Requirement)
There appears to be extra words after colon in this section – Based on the redline there is “requirement will prioritize offers” in the section which is not complete.
18: Please supply any comments on redlines to Tariff section 20.4.1 (relating to how Energy Deployment occurs on Operation Day)
No comments at this time
19: Please supply any comments on redlines to Tariff section 20.4.1.2 and 21.1.4 (relating to reference corrections)
See prompt #13.
20: Please supply any comments on redlines to Tariff sections 20.4.2-20.2.4 (relating to corrections to 85 & 80 minutes before the hour)
No comments at this time.
21: Please supply any comments on redlines to Tariff section 20.8.1 (relating to incorrect conflation of "Raise Hand" with Voluntary Holdback)
No comments at this time.
22: Please supply any comments on redlines to Tariff section 21.2.4 (relating to updating Energy Declined Settlement price to be the Applicable Real-time Index Price for the hour)
No comments at this time.
23: Please supply any comments on redlines to Tariff section 21.2.5 (relating to change to Make Whole Adjustment formula)
No comments at this time.
General Comment
No comments at this time.