RAJ HUNDAL | PWX
JERRET FISCHER | SRP
SRP suggests that BPM 204 explicitly reference any requirements related to bilateral transfers to ensure firm generation (G-F, WSPP Schedule C, etc.) or transmission (7-F, 7-FN, etc.).
NICOLE BLACKWELL | Idaho Pow…
MATT HAYES | BPA
TYLER MOORE | Arizona P…
The first sentence should be amended to be “Participant (A) may agree with any other surplus Participant (B)”.
LINDSEY SCHLEKEWAY | NVE
SANDEAP REDDY | Puget Sou…
In the example provided in Sec. 7 , would Participant B assume liability for potential energy non delivery charges if they were transferred ownership of the Holdback Requirement for Participant A? Please provide clarification
BENJAMIN FAULKINBERRY | PacifiCor…
Please detail what, if any feasibility check is performed by the PIT when a bilateral transfer of Holdback occurs.
Due to industry convention and WRAP requirements, it will be the receiving Participant who ends up needing to re-tag the Holdback delivery if a bilateral transfer occurs. Please elaborate on what recourse a receiving Participant has if a failure occurs, or if the transfer is infeasible for the receiving Participant.
In particular, transmission availability changes from Preschedule Day to Operating Day. If Participant A is scheduled to receive Holdback from Participant B, and Participant B transfers its Holdback obligation to Participant C, but Participant A does not have sufficient inbound transmission available from Participant C, what is the outcome? Please cover this and other avenues of recourse Participant A would have if there is a failure or error between Participant B and Participant C.
GABRIELLE GLYNN | Tacoma Po…
“Requirement transfer shall be a bilateral arrangement settled outside the WRAP, provided, however, that both Participants of such Holdback Requirement transfer must notify the Program Administrator and the Program Operator in a timely manner using the PIT between 07:00 PPT and T-120 on the Operating Day.”
Tacoma would like to clarify that the timeline to notify the PA and PO would be from 07:00 PPT on the Preschedule Day to T-120 on the Operating Day (unless this interpretation is incorrect).