RAJ HUNDAL | PWX
JERRET FISCHER | SRP
SRP encourages the WPP to consider including a process and timeline for participants to petition for early release of Holdback Capacity.
NICOLE BLACKWELL | Idaho Pow…
Idaho Power has general concerns with this section and believes it warrants more discussion. The BPM doesn’t reference any metrics or guidelines for meeting criteria to justify early release of holdback. Idaho Power also supports continued discussion on the extenuating circumstances listed in the BPM that may justify early release of holdback.
MATT HAYES | BPA
What happens if a participant’s request for early release is granted and the participant subsequently experiences a major Forced Outage? For example a release is requested 3 days out and the forced outage occurs just ahead of the preschedule calculation. The participant would now have a negative sharing calculation. How would the program address such a scenario?
TYLER MOORE | Arizona P…
No comments at this time.
LINDSEY SCHLEKEWAY | NVE
SANDEAP REDDY | Puget Sou…
N/A