01: Please supply any comments related to the Introduction, Definitions, or Background sections.




Nov. 6, 2023, 8:52 a.m.
TYLER MOORE | Arizona P…

The first sentence in the Introduction references exigent circumstances as defined in the Tariff, but we believe we should also reference BPM 303 Expedited Review Process in this section as that is the BPM that covers concepts with exigent circumstances.

The third paragraph in the Background section discusses what happens when a concept is approved to be included in the Workplan, but doesn’t speak to what happens to those concepts not approved. APS would recommend including what happens to those in this section or reference BPM 301 Workplan Development if that is more appropriate.


Nov. 2, 2023, 4:03 p.m.
JERRET FISCHER | SRP
No response submitted.