13: Please supply any comments on redlines to Tariff section 19.5 and 20.4.1.2 (relating to reference correction of Subregions not containing a central transmission hub)




July 8, 2024, 2:45 p.m.
RAJ HUNDAL | PWX
No response submitted.

July 9, 2024, 8:18 a.m.
BEN BRANDT | Idaho Pow…
No response submitted.

July 9, 2024, 9:54 a.m.
JERRET FISCHER | SRP

Section 19.5 is difficult to interpret, possibly due to extra commas or suboptimal placement of the “ending on the Preschedule Day” detail.


July 9, 2024, 11:20 a.m.
MATT HAYES | BPA

Rewording is needed for section 19.5 as it lacks precise and clear wording. BPA is happy to discuss further.


July 9, 2024, 11:43 a.m.
BEN BRANDT | Idaho Pow…
No response submitted.

July 9, 2024, 3:01 p.m.
SACHI BEGUR | Puget Sou…
No response submitted.

July 9, 2024, 4:12 p.m.
TYLER MOORE | Arizona P…

In 20.4.1.2 propose to include “…unless mutually agreed to by both deficient and surplus Participants”. This would allow for any arrangement where transmission becomes unavailable to be re-supplied at an alternative location.