Section 5.2 does not tie back to adjusted QCC’s in any way except the ‘additionally’ note. Also, storage hydro adjusted QCC’s should be described here.
This entire section should focus on a theme of adjusted QCC values.
No response submitted.
SRP understands that GADS is the Generator Availability Data System, though this section suggests that GADS is the Generation Availability Data System.
SRP understands that GADS now includes reporting of outage events for VER resources according to the GADS Solar Generation (GADS‐S) – Data Reporting Instructions 2024. SRP requests confirmation that if forecasted VER output considers reductions for expected Forced Outages consistent with GADS reporting, this would be captured in the Δ VER Performance component rather than section 5.2.
The sentence concluding section 5.2 is ambiguous: “Any derate, outage, or transmission curtailment resulting in a reduction of generation capability for must take resources, shall not be accounted for and excluded from Forced Outage forecasts.” SRP requests clarity on whether the phrase is equivalent to “shall not be accounted for and shall be excluded from Forced Outage forecasts” or “shall be neither accounted for nor excluded from Forced Outage forecasts”.
APS believes that are valid GADS codes are not applicable to capturing of forced outages and derates, can we add the applicable GADS types here to be utilized? For example, U1 and D1 are outage and derate immediate GADS codes where PO is a planned outage and shouldn’t be included in the data files submitted by participants.
For the note on must take thermal resources is it not possible a participant submitted historical data to calculate a EFOF, therefore could submit the forced outages associated with the resource in the Operations Program in that scenario?