20: Please supply any comments related to the Planned Outages section (8).




July 25, 2024, 1:17 p.m.
BENJAMIN FAULKINBERRY | PacifiCor…
No response submitted.

July 25, 2024, 1:15 p.m.
MAYA MCNICHOL | WPP
No response submitted.

July 26, 2024, 9:36 a.m.
MATT HAYES | BPA

Bonneville suggests the following additions be made to this section:

The aggregate of any additional outages that are planned to occur during the Binding Season but have not yet begun at FS Submittal deadline must be within the Participant’s remaining surplus or replaced with other supply or incorporated in the calculation of QCC that is submitted in Forward Showing.


July 26, 2024, 2:04 p.m.
LINDSEY SCHLEKEWAY | NVE
No response submitted.

July 29, 2024, 4:24 p.m.
JERRET FISCHER | SRP
No response submitted.

July 29, 2024, 4:51 p.m.
SANDEAP REDDY | Puget Sou…

N/A


July 30, 2024, 12:46 p.m.
TYLER MOORE | Arizona P…

This section is silent on construction delays related to resources expected to be available and shown in the Forward Showing, but then are delayed in the Operations Program. How should such delay be communicated in regards to being a planned or forced outage?