09: Please supply any comments related to the Inputs from the Operations Program - Forecasted solar output section (5.5).




July 25, 2024, 1:17 p.m.
BENJAMIN FAULKINBERRY | PacifiCor…

PacifiCorp would like to further understand how WPP will be verifying Participants’ forecast methodologies, and the consequences associated with not meeting the requirements in this section.


July 25, 2024, 1:15 p.m.
MAYA MCNICHOL | WPP
No response submitted.

July 26, 2024, 9:36 a.m.
MATT HAYES | BPA

Bonneville requests further clarification on the meaning of “regular” and “mitigate” in the following sentence: The Program Administrator/Program Operator will evaluate on a regular basis forecast performance and deviations to identify and mitigate inaccurate data.


July 26, 2024, 2:04 p.m.
LINDSEY SCHLEKEWAY | NVE
No response submitted.

July 29, 2024, 4:24 p.m.
JERRET FISCHER | SRP
No response submitted.

July 29, 2024, 4:51 p.m.
SANDEAP REDDY | Puget Sou…

By what criteria will the PO/PA determine whether a given participant’s forecast methodology is sufficiently inaccurate and therefore requires mitigation. Will Participants need to share their actual forecasting methodology for PO/PA evaluation?


July 30, 2024, 12:46 p.m.
TYLER MOORE | Arizona P…

No comments at this time.